February 14 Update

Look-Ahead Update
Special Notes:
*Intersection of 34th and P Street now OPEN
*Completed section of roadway on the 3300 Block of P Street (North Side) scheduled to OPEN on or about February 22

Updated 2-14-12:
*All scheduled dates shown are dependent on weather conditions and subject to change.

Location & Work:
P Street
3200 Block of P Street (North Side)
• Installation of electrical conduits and manhole (February 16-February 24)
• Installation of maintenance of traffic barriers toward Wisconsin Avenue (February 20)
• Removal of cobblestones and bluestone curb (February 14-February 17)
• Excavation of roadway; installation of GAB and Geofabric material (February 15-February 24)
• Removal of streetcar track rails, manhole and junction boxes (February 14-February 17)

3300 Block of P Street (North Side)
• Installation of PCC base (February 14)
• Installation of cobblestone on roadway and gutter (February 14-February 24)
• Installation of street light foundations (February 22-February 24)
Open completed section of the roadway (February 22)

33rd and P Street Northwest Intersection
• Set maintenance of traffic barriers (February 20)
• Excavation of roadway; installation of GAB and Geofabric material (February 21-February 24)
• Installation of PCC base (February 24)

34th and P Street (Northeast Side)
• Installation of granite cub, wheelchair ramps, brick gutter and brick sidewalk (February 14-February 17)
• Installation of street light foundations (February 22-February 24)
Open Intersection (February 14)

O Street
3200 Block of O Street (North Side) between Potomac Street and Wisconsin Avenue
• Water service replacement – South Side (February 14-February 17)
• Water service replacement – North Side (February 20-February 24)
• Installation of fire hydrant (February 14)